Colbert Quarter

Colbert Quarter covers a development land size of 46.9 hectares - it will be brought forward using a phased approach. The lands have the potential for 2,540 - 2,830 new homes in addition to various communal and commercial space.

image

General Overview

Project Status: Delayed

Project Type: Mixed Use

Project Start: 2019

Project Location: Limerick

Project Details

  • Name: Colbert Quarter
  • Owner: The Land Development Agency (LDA)
  • Location: Lands Adjacent to Colbert Station, Limerick
  • When site was acquired: Lands in existing state ownership
  • Estimated project cost (€): €1 - €2 Billion
  • Estimated Project Completion Date: 2035
  • Date Page Last Updated: 06.04.2023
  • Link to Website: https://colbertquarter.ie/
  • Public consultations: Numerous undertaken so far

Preliminary Phases Status

Preliminary Phases

Phase Start Date Finish Date Phase Status Comments
Project Conception Oct-19

complete

Infrastructure & Delivery 2020 Q2-23

started

Tendering Phases

Phase Start Date Finish Date Phase Status Comments
Appointment of Design Review Team

complete

Tendering & Appointment for Spatial Framework

complete

Tendering & Appointment of Planning Services

complete

Tendering & Appointment of Construction Est. Q2-24 Est. Q2-24

on-schedule

Planning Phases

Phase Start Date Finish Date Phase Status Comments
Design Review Mar-20 Sep-20

complete

Spatial Framework Q1-21 Q2-22

complete

Finalised May 22
Master Planning / Planning Design Sep-22 Est. Q2-23

delayed

Masterplan for St. Joseph's site was due to be released in Summer 2023, it did not meet this deadline
Planning Submission & Approval Est. Q4-23 Est. Q2-25

not-started

Construction Phases

Phase Start Date Finish Date Phase Status Comments
Commencement of Works on Site Est. Q1-26

not-started

Phased approach to commencement and delivery
Project Completion Est. 2035

not-started

Phased approach to commencement and delivery