The project comprises 36 No. residential units which includes 25 No. 2 Beds and 11 No. 1 Beds. The site has excellent access to public open space in the immediate area. The site lies adjacent to People’s Park Limerick and Hyde Road Park is located directly opposite.
General Overview
Project Status: On-schedule
Project Type: Residential
Project Start: 2020
Project Location: Limerick
Project Details
- Name: Speaker's Corner
- Owner: Limerick City & County Council
- Location: Lower Carey's Road, Limerick City
- When site was acquired: Existing Local Authority Ownership
- Funding Allocated (€) & Source of funds: To be developed by Whitebox Ltd & Cluid Housing
- Estimated Project Completion Date: To be confirmed following planning permission grant
- Date Page Last Updated: 06.04.2023
- Link to Website: https://www.limerick.ie/
- Public consultations: Complete
Preliminary Phases Status
Preliminary Phases
Phase | Start Date | Finish Date | Phase Status | Comments |
---|---|---|---|---|
Project Conception | Nov-20 | complete |
||
Complete Site Ownership | started |
Tendering Phases
Phase | Start Date | Finish Date | Phase Status | Comments |
---|---|---|---|---|
Tendering and Appointment - Planning Services | Nov-20 | Dec-20 | complete |
|
Tendering and Appointment - Construction | Nov-20 | complete |
Planning Phases
Phase | Start Date | Finish Date | Phase Status | Comments |
---|---|---|---|---|
Master Planning / Planning Design | Jan-21 | Aug-22 | complete |
|
Planning Submission and Approval | Aug-22 | Nov-22 | complete |
Construction Phases
Phase | Start Date | Finish Date | Phase Status | Comments |
---|---|---|---|---|
Commencement of Works on Site | not-started |
|||
Project Completion | not-started |