Back to all projects

Cleeves Riverside Quarter

The iconic 10-acre former Cleeves factory site is located on the northern bank of the River Shannon. The majority of the site is zoned City Centre Area in the Limerick Development Plan and is suited to a mix of uses including; residential, office, educational, visitor attraction and public realm.

image

General Overview

Project Status: On-schedule

Project Type: Mixed Use

Project Start: 2014

Project Location: Limerick

Project Details

  • Name: Cleeves Riverside Quarter
  • Owner: Limerick Twenty Thirty
  • Location: Former Cleeves Factory, O'Callaghan Strand, Limerick
  • When site was acquired: Limerick City and County Council Purchased Site (Cleeves & Salesians) in 2014 and 2017 for €4.1 million
  • Estimated project cost (€): €300 million
  • Funding Allocated (€) & Source of funds: €34.5 million of Urban Regeneration and Development Fund (URDF Call 2) (As part pf €73.4 million total for world class waterfront)
  • Estimated Project Completion Date: 2030 (Estimation) - Dates are indicative only and are subject to planning permission, market demand and availability of finance
  • Date Page Last Updated: 06.04.2023
  • Link to Website: https://limerick2030.ie/cleeves-riverside-campus/
  • Public consultations: Target Q1 2023 for public consultation

Preliminary Phases Status

Preliminary Phases

Phase Start Date Finish Date Phase Status Comments
Project Conception Sep-14

complete

Complete Site Ownership Sep-14

complete

Tendering Phases

Phase Start Date Finish Date Phase Status Comments
Measured Building Survey Mar-19 Apr-19

complete

Development Consultants Jul-19 Aug-19

complete

Preliminary Ground Investigation Oct-21 Oct-21

complete

Planning Tendering & Appointment Mar-19 Sep-20

complete

Construction Tendering & Appointment

not-started

Planning Phases

Phase Start Date Finish Date Phase Status Comments
Master Planning Sep-20 Q1-23

complete

Master plan launched in Q1-23 - expected to be finalised May 2023. Masterplan was finalised and published in Nov-23
Planning Submission & Approval

delayed

Submission Est. 2024

Construction Phases

Phase Start Date Finish Date Phase Status Comments
Commencement of Works on Site

not-started

Project Completion

not-started

Est. 2030