Bannatyne Mills
SFPC has embarked on a programme to transform the Bannatyne Mill building to stunning commercial property. The project will transform this remarkable building into a modern office space ideal for the services sector and capable of accommodating up to 430 employees.
General Overview
Project Status: Delayed
Project Type: Commercial & Office Space
Project Start: 2018
Project Location: Limerick
Project Details
- Name: Bannatyne Mills
- Owner: Shannon Foynes Port Company (SFPC)
- Location: Limerick Port, Dock Road, Limerick
- When site was acquired: Existing Ownership
- Estimated project cost (€): €8 million
- Funding Allocated (€) & Source of funds: Funding & Debt
- Estimated Project Completion Date: H1-2024. New Estimate not provided.
- Date Page Last Updated: 24.02.2025
- Link to Website: https://www.sfpc.ie/bannatyne-mills-development/
Preliminary Phases Status
Preliminary Phases
| Phase | Start Date | Finish Date | Phase Status | Comments |
|---|---|---|---|---|
| Feasibility Study | complete |
|||
| Project Conception | complete |
|||
| Complete Site Ownership | complete |
Tendering Phases
| Phase | Start Date | Finish Date | Phase Status | Comments |
|---|---|---|---|---|
| Tendering & Appointment of Planning Services | complete |
|||
| Tendering & Appointment of Main Works | Dec-22 | complete |
||
| Tendering & Appointment of Other Construction | May-22 | Sep-22 | complete |
Engineering & QS |
Planning Phases
| Phase | Start Date | Finish Date | Phase Status | Comments |
|---|---|---|---|---|
| Master Planning / Planning Design | complete |
|||
| Planning Submission & Approval | Oct-19 | Dec-19 | complete |
Construction Phases
| Phase | Start Date | Finish Date | Phase Status | Comments |
|---|---|---|---|---|
| Commencement of Works on Site | not-started |
Currently at pre-funding stage | ||
| Project Completion | delayed |