General Overview
Project Status: On-schedule
Project Type: Healthcare
Project Start: 2020
Project Location: Limerick
Project Details
- Name: Bon Secours Hospital, Ballysimon
- Owner: Bon Secours Health System
- Location: Groody Road, Ballysimon, Limerick
- When site was acquired: December 2020
- Estimated project cost (€): €150 million
- Funding Allocated (€) & Source of funds: Bon Secours Mercy Health
- Estimated Project Completion Date: Estimated Q1 2025
- Date Page Last Updated: 19.10.2022
- Link to Website: https://www.bonsecours.ie/limerick/news/bon-secours-health-systems-hospital-limerick
Preliminary Phases Status
Preliminary Phases
Phase | Start Date | Finish Date | Phase Status | Comments |
---|---|---|---|---|
Feasibility Study | Jan-20 | Mar-20 | complete |
|
Project Conception | Mar-20 | Feb-21 | complete |
|
Complete Site Ownership | Sep-20 | Dec-20 | complete |
Tendering Phases
Phase | Start Date | Finish Date | Phase Status | Comments |
---|---|---|---|---|
Tendering & Appointment of Planning Services | Mar-21 | Aug-21 | complete |
|
Tendering & Appointment of Construction | Sep-22 | Q1-23 | complete |
Planning Phases
Phase | Start Date | Finish Date | Phase Status | Comments |
---|---|---|---|---|
Master Planning / Planning Design | Jun-21 | Dec-21 | complete |
|
Pre-application Consulataion | Sep-21 | Nov-21 | complete |
|
Planning Submission & Approval | Aug-21 | Jun-22 | complete |
Construction Phases
Phase | Start Date | Finish Date | Phase Status | Comments |
---|---|---|---|---|
Commencement of Works on Site | Feb-23 | started |
The project officially broke ground in Feb-23 | |
Project Completion | Est. Q1-25 | on-schedule |