N69 – Foynes to Limerick Road and Adare Bypass

Provision of M21 Motorway from Patrickswell to Rathkeale and a Dual Carriageway from Rathkeale to Foynes

image

General Overview

Project Status: Delayed

Project Type: Transport

Project Start: 2022

Project Location: Limerick

Project Details

  • Name: N69 - Foynes to Limerick Road (including Adare Bypass)
  • Owner: Mid West Road Design Office (MWRDO) (Limerick City and County Council)
  • Location: Limerick
  • When site was acquired: Lands Not Acquired
  • Estimated project cost (€): €455 million
  • Funding Allocated (€) & Source of funds: €10 million allocated in 2022 from Transport Infrastructure Ireland (TII)
  • Estimated Project Completion Date: Est. 2027
  • Date Page Last Updated: 03.12.2024
  • Link to Website: https://www.foyneslimerick.ie/

Preliminary Phases Status

Preliminary Phases

Phase Start Date Finish Date Phase Status Comments
Feasibility Study

complete

Project Conception

complete

Complete Site Ownership

started

Tendering Phases

Phase Start Date Finish Date Phase Status Comments
Tendering & Appointment of Planning Services

complete

Tendering & Appointment of Construction (Adare Bypass Only) Jun-24

complete

Planning Phases

Phase Start Date Finish Date Phase Status Comments
Masterplanning / Planning design

complete

Pre-application consultation

complete

Planning Submission & Approval

complete

Construction Phases

Phase Start Date Finish Date Phase Status Comments
Commencement of works on site

delayed

The project was delayed due to judicial review proceedings. These judicial reviews were withdrawn in June 2023.
Project Completion Est. 2027

not-started