N69 – Foynes to Limerick Road
General Overview
Project Status: Delayed
Project Type: Transport
Project Start: 2022
Project Location: Limerick
Project Details
- Name: N69 - Foynes to Limerick Road (including Adare Bypass)
- Owner: Mid West Road Design Office (MWRDO) (Limerick City and County Council)
- Location: Limerick
- When site was acquired: Lands Not Acquired
- Estimated project cost (€): €455 million
- Funding Allocated (€) & Source of funds: €10 million allocated in 2022 from Transport Infrastructure Ireland (TII)
- Estimated Project Completion Date: Est. 2027
- Date Page Last Updated: 09.01.2025
- Link to Website: https://www.foyneslimerick.ie/
Preliminary Phases Status
Preliminary Phases
| Phase | Start Date | Finish Date | Phase Status | Comments |
|---|---|---|---|---|
| Feasibility Study | complete |
|||
| Project Conception | complete |
|||
| Complete Site Ownership | started |
Tendering Phases
| Phase | Start Date | Finish Date | Phase Status | Comments |
|---|---|---|---|---|
| Tendering & Appointment of Planning Services | complete |
|||
| Tendering for construction and remaining elements | Est. 2026 or 2027 | not-started |
Planning Phases
| Phase | Start Date | Finish Date | Phase Status | Comments |
|---|---|---|---|---|
| Masterplanning / Planning design | complete |
|||
| Pre-application consultation | complete |
|||
| Planning Submission & Approval | complete |
Construction Phases
| Phase | Start Date | Finish Date | Phase Status | Comments |
|---|---|---|---|---|
| Commencement of works on site | delayed |
The project was delayed due to judicial review proceedings. These judicial reviews were withdrawn in June 2023. No further commencement information has been provided by the Mid-West Road Design Office | ||
| Project Completion | not-started |
No completion information has been provided by the Mid-West Roads Office on Completion |