Project Opera

The 3.7-acre project at Opera Square is a landmark commercial development in Limerick City. The project will be capable of employing up to 3,000 people across a 450,000 sq ft campus designed to international best practice LEED Gold and ‘NZEB’ standards of project development.

image

General Overview

Project Status: On-schedule

Project Type: Mixed Use

Project Start: 2011

Project Location: Limerick

Project Details

  • Name: Project Opera
  • Owner: Limerick Twenty Thirty
  • Location: Opera Site, Patrick Street, Limerick City
  • When site was acquired: Limerick City and County Council Purchased Site in 2011 for €12.5 million
  • Estimated project cost (€): c. €290 million
  • Funding Allocated (€) & Source of funds: €170 million (European Investment Bank and Council of Europe Development Bank Loans) and €1.8 million in URDF call 1, €80 million funding from ISIF as part of a joint venture partnership
  • Estimated Project Completion Date: Phase 1 Est. Dec 2025
  • Date Page Last Updated: 13.01.2025
  • Link to Website: https://limerick2030.ie/opera-site/
  • Public consultations: Undertaken in November 2021

Preliminary Phases Status

Preliminary Phases

Phase Start Date Finish Date Phase Status Comments
Project Conception Nov-11

complete

Complete Site Onwership Nov-11

complete

Tendering Phases

Phase Start Date Finish Date Phase Status Comments
Planning Tendering & Appointment - One Opera Square Oct-21

complete

Planning Tendering & Appointment - Commercial Tower, Library & Courtyard Sep-21

complete

Construction Tendering & Appointment - Demolition May-19 Nov-19

complete

Construction Tendering & Appointment - Basement and One Opera Square Nov-21 Dec-22

complete

Contractor announced in Feb 23
Construction Tendering & Appointment - Commercial Tower, Library & Courtyard Nov-22 Jan-24

complete

Construction Tendering & Appointment - Library, Four Opera Sq office and Central Plaza Dec-24 Feb-25

on-schedule

Planning Phases

Phase Start Date Finish Date Phase Status Comments
Master Planning May-17 Dec-18

complete

Planning Submission & Approval Mar-19 Feb-20

complete

Planning Amendments Submission & Approval Nov-22 Jan-24

complete

One further amendment to be submitted for hotel site in Q1 2025

Construction Phases

Phase Start Date Finish Date Phase Status Comments
Commencement of Works on Site Nov-20

started

Completion - Sitewide Basement and One Opera Square Building Apr-25

on-schedule

Completion - Library Est. 2025 Est. 2027

not-started

* Subject to funding
Completion - 14-Storey Landmark Building Est. 2025 Est. 2027

not-started

* Subject to funding