Project Opera
The 3.7-acre project at Opera Square is a landmark commercial development in Limerick City. The project will be capable of employing up to 3,000 people across a 450,000 sq ft campus designed to international best practice LEED Gold and ‘NZEB’ standards of project development.
General Overview
Project Status: On-schedule
Project Type: Mixed Use
Project Start: 2011
Project Location: Limerick
Project Details
- Name: Project Opera
- Owner: Limerick Twenty Thirty
- Location: Opera Site, Patrick Street, Limerick City
- When site was acquired: Limerick City and County Council Purchased Site in 2011 for €12.5 million
- Estimated project cost (€): c. €290 million
- Funding Allocated (€) & Source of funds: €170 million (European Investment Bank and Council of Europe Development Bank Loans) and €1.8 million in URDF call 1, €80 million funding from ISIF as part of a joint venture partnership
- Estimated Project Completion Date: Phase 1 Est. Dec 2025
- Date Page Last Updated: 06.04.2023
- Link to Website: https://limerick2030.ie/opera-site/
- Public consultations: Undertaken in November 2021
Preliminary Phases Status
Preliminary Phases
Phase | Start Date | Finish Date | Phase Status | Comments |
---|---|---|---|---|
Project Conception | Nov-11 | complete |
||
Complete Site Onwership | Nov-11 | complete |
Tendering Phases
Phase | Start Date | Finish Date | Phase Status | Comments |
---|---|---|---|---|
Planning Tendering & Appointment - One Opera Square | Oct-21 | complete |
||
Planning Tendering & Appointment - Commercial Tower, Library & Courtyard | Sep-21 | complete |
||
Construction Tendering & Appointment - Demolition | May-19 | Nov-19 | complete |
|
Construction Tendering & Appointment - Basement and One Opera Square | Nov-21 | Dec-22 | complete |
Contractor announced in Feb 23 |
Construction Tendering & Appointment - Commercial Tower, Library & Courtyard | Nov-22 | Jan-24 | started |
Planning Phases
Phase | Start Date | Finish Date | Phase Status | Comments |
---|---|---|---|---|
Master Planning | May-17 | Dec-18 | complete |
|
Planning Submission & Approval | Mar-19 | Feb-20 | complete |
|
Planning Amendments Submission & Approval | Nov-22 | started |
ABP decision for additional permission is ongoing |
Construction Phases
Phase | Start Date | Finish Date | Phase Status | Comments |
---|---|---|---|---|
Commencement of Works on Site | Nov-20 | started |
||
Phase 1 Completion | Est. Dec 2025 | on-schedule |