World-Class Waterfront
The world class waterfront contains two projects, the Cleeves Riverside Quarter and public realm and development works along the River Shannon. The Cleeves Riverside Quarter is outlined as a separate project on the Strategic Development Pipeline, this page excludes Cleeves Riverside Quarter.
General Overview
Project Status: Delayed
Project Type: Public Realm
Project Start: 2021
Project Location: Limerick
Project Details
- Name: World-Class Waterfront
- Owner: Limerick City & County Council
- Location: Bordering the River Shannon in Limerick City
- When site was acquired: Public Ownership
- Estimated project cost (€): TBC
- Funding Allocated (€) & Source of funds: €38.4 million of Urban Regeneration and Development Fund (URDF Call 2) (As part pf €73.4 million total for world class waterfront including Cleeves Riverside Campus) and €350,000 from call 1 of URDF
- Estimated Project Completion Date: TBC
- Date Page Last Updated: 22.11.2023
- Link to Website: https://www.limerick.ie/council/newsroom/news/limerick-city-and-county-council-welcomes-multi-million-euro-investment
- Public consultations: TBC
Preliminary Phases Status
Preliminary Phases
Phase | Start Date | Finish Date | Phase Status | Comments |
---|---|---|---|---|
Project Conception | Mar-21 | complete |
Tendering Phases
Phase | Start Date | Finish Date | Phase Status | Comments |
---|---|---|---|---|
Tender for Urban Framework Plan | 11th Nov 2022 | complete |
Arthur's Quay Area Only | |
Tendering for Plan for Remaining Area (outside Arthur's Quay Area) | tbc |
|||
Tendering & Appointment of Planning Services | not-started |
|||
Tendering & Appointment of Construction Services | not-started |
Planning Phases
Phase | Start Date | Finish Date | Phase Status | Comments |
---|---|---|---|---|
Preparation of Framework Plan (Arthur's Quay Area) | Q4 2023 | complete |
The project did not meet the Q4'23 deadline, or the new Q1'24 deadline. The public consultation for the framework plan launched in Oct. 24 and closed in Nov. 24 | |
Preparation of Framework Plan (Remaining Area) | not-started |
|||
Master Planning / Planning Design | not-started |
|||
Planning Submission & Approval | not-started |
Construction Phases
Phase | Start Date | Finish Date | Phase Status | Comments |
---|---|---|---|---|
Commencement of Works on Site | not-started |
|||
Project Completion | not-started |