Francis Street – Ennis
The proposed development will comprise a Mixed-Use Development to include retail/commercial use at ground floor level and office accommodation suitable for Corporate Headquarters on the upper floors. The building will be sustainable and energy efficient in line with LEED Platinum standards.
General Overview
Project Status: On-schedule
Project Type: Mixed Use
Project Start: 2022
Project Location: Clare
Project Details
- Name: Francis Street, Ennis
- Owner: Ennis 2040 (Strategic Development) D.A.C.
- Location: Francis Street, Causeway Link Road, Ennis, Co. Clare
- When site was acquired: August 2022
- Estimated project cost (€): €20 million
- Estimated Project Completion Date: May 2026
- Date Page Last Updated: 06.04.2023
- Link to Website: https://www.ennis2040.ie
Preliminary Phases Status
Preliminary Phases
Phase | Start Date | Finish Date | Phase Status | Comments |
---|---|---|---|---|
Fesibility Study | May-23 | delayed |
||
Project Conception | Nov-22 | complete |
||
Complete Site Ownership | Q2-23 | delayed |
Tendering Phases
Phase | Start Date | Finish Date | Phase Status | Comments |
---|---|---|---|---|
Tendering & Appointment of Planning Services | Oct-23 | Oct-23 | not-started |
|
Tendering & Appointment of Construction Services | Oct-24 | Oct-24 | not-started |
Planning Phases
Phase | Start Date | Finish Date | Phase Status | Comments |
---|---|---|---|---|
Master Planning / Planning Design | May-23 | delayed |
||
Pre-Application Consultation | Oct-23 | not-started |
||
Planning Submission & Approval | Oct-23 | Oct-24 | not-started |
Construction Phases
Phase | Start Date | Finish Date | Phase Status | Comments |
---|---|---|---|---|
Commencement of Works on Site | Oct-24 | not-started |
||
Project Completion | Est. May-26 | not-started |