Back to all projects

N/M20 Limerick to Cork

Improvements required to the N20 was identified in 1998. This was stated as a Government objective in the 2000-2006 National Development Plan. In 2008 a study was commissioned and in 2010 proposals were lodged with An Bord Pleanála (later withdrawn.) In 2022 a preferred route was identified.

image

General Overview

Project Status: On-schedule

Project Type: Transport

Project Location: Limerick

Project Details

  • Name: N/M20 Limerick to Cork
  • Owner: Mid West National Road Design Office (MWNRDO) (Limerick City and County Council)
  • Location: Limerick
  • When site was acquired: Lands required but not yet identified
  • Estimated project cost (€): Reported to be €1 - €1.5 Billion - however, full amount to be developed as part of the Phase 3 Business Case
  • Funding Allocated (€) & Source of funds: €6 million allocated in 2022 from Transport Infrastructure Ireland (TII)
  • Estimated Project Completion Date: 2030 (Best case scenario)
  • Date Page Last Updated: 27.11.2023
  • Link to Website: https://corklimerick.ie/
  • Public consultations: Public Consultation commenced on the 19th November 2020 and following great interest from the public the original closing date of 18th December 2020 was extended to the 15th January 2021. Advertising of the event was repeated in 8 national and regional newspapers, on 3 local radio stations, local authority websites and social media, displayed in 7 public buildings and a targeted letter drop was undertaken.

Preliminary Phases Status

Preliminary Phases

Phase Start Date Finish Date Phase Status Comments
Feasibility Study

complete

Project Conception 1998

complete

Complete Site Ownership

tbc

Tendering Phases

Phase Start Date Finish Date Phase Status Comments
Tendering and Appointment of Planning Services

complete

Tendering & Appointment Engineering Services April-18 May-19

complete

Tendering & Appointment Topographical Survey Mar-23

on-schedule

Tendering & Appointment Archeological Services Jul-22

started

Tendering and Appointment of Construction

not-started

Planning Phases

Phase Start Date Finish Date Phase Status Comments
Draft Design Publication Q2-24

not-started

Final Drawings and Fence Line Q4-24

not-started

Permission from Government to apply to ABP 2025

not-started

Construction Phases

Phase Start Date Finish Date Phase Status Comments
Commencement of works on site

not-started

Project Completion

not-started