Back to all projects
UL Student Centre
The new Student Centre, a 3,529 sq. m. building set over three storeys, is in a ‘Centre for Student Life’ as articulated by the students - will support the student journey through UL and will be a space where students can relax, play, be informed and supported.
General Overview
Project Status: On-schedule
Project Type: Education
Project Start: 2016
Project Location: Limerick
Project Details
- Name: Student Centre, University of Limerick
- Owner: University of Limerick
- Location: University of Limerick, Main Campus, Plassey
- When site was acquired: Existing University Ownership
- Estimated project cost (€): C. €30 million
- Funding Allocated (€) & Source of funds: 80% of capital funding through a student development levy
- Estimated Project Completion Date: 2024
- Date Page Last Updated: 28.04.2023
- Link to Website: https://www.ul.ie/
Preliminary Phases Status
Preliminary Phases
Phase | Start Date | Finish Date | Phase Status | Comments |
---|---|---|---|---|
Feasability Study | complete |
|||
Project Conception | Apr-16 | complete |
Tendering Phases
Phase | Start Date | Finish Date | Phase Status | Comments |
---|---|---|---|---|
Tendering & Appointment of Planning Services | Aug-16 | Feb-17 | complete |
|
Tendering & Appointment Construction Works 1 | Apr-18 | Jul-19 | complete |
|
Tendering & Appointment Construction Works 2 | Nov-20 | complete |
||
Tendering & Appointment Construction Works 3 | Jul-22 | Aug-22 | complete |
Planning Phases
Phase | Start Date | Finish Date | Phase Status | Comments |
---|---|---|---|---|
Master Planning / Planning Design | Feb-17 | Dec-17 | complete |
|
Planning Submission & Approval | Dec-17 | May-18 | complete |
Construction Phases
Phase | Start Date | Finish Date | Phase Status | Comments |
---|---|---|---|---|
Commencement of Works on Site | May-19 | started |
Works recommenced Mar-23 | |
Project Completion | Est. 2024 | on-schedule |